Challenge

The customer needed to build a thermal power plant building in Yerevan, Armenia.

Solution

For the construction of the thermal power plant building, ProfHolod manufactured:

  • more than 3,300 sq. m of roof panels with mineral wool, 120 mm thick, color RAL 7015/9003
  • more than 2,300 sq. m of wall panels with mineral wool, 120 mm thick, color RAL 9006/9003

For the construction of the additional structures of the thermal power plant, ProfHolod manufactured:

  • more than 700 sq. m of roof panels with mineral wool, 120 mm thick, color RAL 7015/9003
  • more than 1,000 sq. m of wall panels with mineral wool, 120 mm thick, color RAL 9006/9003